How to build a capital stack and find the financing gap

Start from what the project costs, subtract what the bank will lend against its income, then subtract every other source you have. What is left is the gap, and naming it in dollars is the first step to closing it.

How to work it out

  1. Total the development cost. Land, hard costs, soft costs and reserves: every dollar it takes to finish. This is the height the stack has to reach.
  2. Size the senior loan from income. A lender divides the building's net operating income by a coverage ratio (often 1.20 to 1.25) to get the most annual debt service it will accept, then turns that into a loan amount at its rate and term.
  3. Add equity. The sponsor's cash, and any investor equity.
  4. Layer in the rest. Tax credit equity, grants, soft loans from a city or state, and a deferred developer fee, in the order the deal can get them.
  5. Name the gap. Cost minus every source. If it is not zero, the deal needs another source, a lower cost, or more income.

A worked example

A project costs $4,000,000. Its stabilized NOI is $260,000 a year. The sponsor has $400,000 of equity and a $250,000 grant.

What to have ready

Do it in CapStack, free, in your browser. CapStack sizes the senior loan from your NOI, lets you tap in each source (tax credits, grants, soft loans, a deferred developer fee, equity) and shows the gap, the blended cost of capital and how the stack fits together.

Open CapStack

The rate, term and coverage ratio in the example are illustrations. A lender sets its own, and a tax credit's equity depends on the program and the market.

More free guides

Which grants fit your organization? A 10-minute checkDoes the building pay? NOI and DSCR, worked outWhat a lender-ready market study includesFrom a lot to a site plan: setbacks and buildable areaHow to explain a housing project to an architect, a contractor or a lenderHow to size the market for a new locationHow to find your break-even point and your runway